Central St. between Sheridan Rd. and Orrington Ave. will be temporarily closed for four to five hours on Friday, February 24, 2012 in order for a crane to hoist and install a generator.

The closure will begin at 9 a.m. with a detour route of Central St. to Sherman Ave. to Lincoln St. to Sheridan Rd. Local traffic will be allowed to enter Central St. up to the work area. See detour map here>>>

The project is under the supervision of Gatwood Crane Service and AEC Electric. For any problems or questions with the project, contact: Mark Schiltz with Gatewood Crane Service at 847/364-1400 or Al Baba with AEC Electric at 847/588-3830. The City of Evanston contact for this project is Pelayo Enerio Jr., Division of Engineering, 847/448-4311.