Two lanes of Davis Street will be temporarily closed from 7 a.m. to 4 p.m., Tuesday, March 26 (westbound, from Chicago Avenue to just past the west alley access side of 614 Davis Street). The temporary closure is in order to complete installation of rooftop mechanical equipment on the main roof of the building project located at 614 Davis Street.

The sidewalk will remain open along the south side of Davis Street between Chicago Avenue and Orrington Avenue with pedestrian traffic being controlled with on-site flaggers. The temporary Davis Street road closure is expected to be completed by the end of the same work day.

Please note: westbound traffic will be merged to the right. One lane of westbound traffic will be maintained throughout the day. Working hours will be from 7:00 a.m. to 4:30 p.m.

Map here>>>

CONTRACTOR:
The construction manager overseeing the temporary street closure and construction is:
The Timm T. Martin Company
3647 Woodhead Drive
Northbrook, Illinois 60062
Office: 847/498-8960

CONTRACTOR SUPERVISION:
David Rodriguez: 773/931-3389

CITY CONTACT:
Questions regarding this work can be addressed to the City of Evanston, Pelayo Enerio Jr. (Jhun), Division of Engineering by dialing 3-1-1.