Construction crews will be installing a new storm water line for the Central Station Apartments at 1700 Central St. from April 22 to May 6. The work includes the installation of a new 4-inch storm water line from the northeast corner of the building at 1700 Central Street to the storm water main in the center of Central Street. Workers will also be completing disconnects of the existing utilities on Eastwood Avenue. This work will include the following: cutting open the road, installing storm pipe, completing disconnects and pavement restoration.
One lane of traffic in each direction will be maintained utilizing traffic controls. Parking in areas will be restricted as needed. The sidewalk on the south side of Central Street will be closed at times. There will be flaggers assisting pedestrians and traffic at all times during working hours.